<< All Blocks Reinitialized >>
<< Run reinitialized 14:28:05 Fri Apr 25, 2014>>
->Processing input specifications ...
Flowsheet Analysis :
COMPUTATION ORDER FOR THE FLOWSHEET:
DIST
->Calculations begin ...
Block: DIST Model: RADFRAC
Convergence iterations:
OL ML IL Err/Tol
1 1 3 714.52
2 1 4 444.79
3 1 5 227.38
4 1 3 86.355
5 1 3 18.362
6 1 3 4.2798
7 1 3 1.3158
8 1 3 0.33326
* WARNING
MURPHREE EFFICIENCY FOR THE LAST STAGE IS IGNORED.
->Simulation calculations completed ...
*** No Warnings were issued during Input Translation ***
*** Summary of Simulation Errors ***
Physical
Property System Simulation
Terminal Errors 0 0 0
Severe Errors 0 0 0
Errors 0 0 0
Warnings 0 0 1
INFORMATION
TPSAR MESSAGE: 102.52% JET FLOOD IN COLUMN DIST , SECTION 1
EXCEEDS 80%.
INFORMATION
TPSAR MESSAGE: SECTION 1 IN COLUMN DIST
IS ABOVE 100% JET FLOOD. HOWEVER, THE DOWNCOMERS
HAVE SPARE CAPACITY. TRY DECREASING DOWNCOMER WIDTHS.
调了下板数和进料位置还是不对
|
评分
-
查看全部评分
|